Helping a leading meat processor reaching its sustainable development goals

14-06-2019

WATERLEAU, as the EPC contractor of the Emerald Bio Energy unit, France's largest industrial biogas plant with a record capacity of 156,000 tons/year, is proud to have participated in its inauguration on June 13, 2019.

Co-products from pig farming and processing will enable to produce 79 million kwh/year, injected into the GRDF network and covering the equivalent of the needs of 3,100 housing units of around 100 m². 

Waterleau provides the entire anaerobic digestion process, from the mixing and dilution of inputs to biogas production. 100% of the input is valorized avoiding discharge. The flexible and unique design of the BIOTIM® wet process technology, based on Waterleau's solid experience in industrial biogas plants, will enable the operation to be highly reliable and robust.

 

Traduction

Waterleau, en tant que concepteur et constructeur de l’unité Emeraude Bio Énergie, le plus gros méthaniseur industriel français d’une capacité record de 156 000 tonnes/an, est fier d’avoir participé à son inauguration le 13 juin 2019.

Les co-produits issus de l’élevage et de la transformation du porc seront valorisés en 79 millions de kwh/an, injectés dans le réseau GRDF et couvrant l'équivalent des besoins de 3 100 logements de 100 m² environ.

Waterleau fournit l’ensemble du processus de méthanisation, depuis le mélange et la dilution des intrants jusque la production de biogaz. 100 % de ce qui y est remis est revalorisé. Le dimensionnement flexible et unique de la technologie BIOTIM® Voie humide, basé sur la solide expérience de Waterleau en méthanisation industrielle, permettra au futur opérateur une grande fiabilité et robustesse dans l’exploitation.